Cement Up ₹7 a Bag in September, More Hikes Possible in October — But the Channel Had Other Ideas·Morbi Supply Returns as Kajaria Targets H2 Recovery: Is the Price Gap Reopening?·Apollo Pipes Buys 76% of Morbi Tile Maker Mazzini for ₹40.42 Crore·Apollo Pipes Board Approves ₹300 Crore Entry Into Tiles and Ceramics·Cersaie and TECNA Open in Italy This Month·India’s Tile Exports Fell 38.8% in Q1 FY27, Not 70% — and Had Largely Recovered by June·India Records Warmest August Since 1901, Monsoon Rainfall Deficit Hits 13.8%·Prestige Estates Launches ₹1,330 Crore Residential Project in Chennai·West Asia Crisis Re-Escalates, Indraprastha Gas Hikes CNG Prices in Delhi-NCR·NBCC Signs Pan-India MoU With NHPC — Residential and Office Infrastructure Pipeline Opens for Building Materials Trade·Cement Up ₹7 a Bag in September, More Hikes Possible in October — But the Channel Had Other Ideas·Morbi Supply Returns as Kajaria Targets H2 Recovery: Is the Price Gap Reopening?·Apollo Pipes Buys 76% of Morbi Tile Maker Mazzini for ₹40.42 Crore·Apollo Pipes Board Approves ₹300 Crore Entry Into Tiles and Ceramics·Cersaie and TECNA Open in Italy This Month·India’s Tile Exports Fell 38.8% in Q1 FY27, Not 70% — and Had Largely Recovered by June·India Records Warmest August Since 1901, Monsoon Rainfall Deficit Hits 13.8%·Prestige Estates Launches ₹1,330 Crore Residential Project in Chennai·West Asia Crisis Re-Escalates, Indraprastha Gas Hikes CNG Prices in Delhi-NCR·NBCC Signs Pan-India MoU With NHPC — Residential and Office Infrastructure Pipeline Opens for Building Materials Trade
Policy & Regulation

Punjab RERA Rejects Covid Excuse – Omaxe Directed to Pay ₹56 Lakh for Possession Delay

July 19, 2026 Distributors & Dealers

Punjab RERA has directed Omaxe’s New Chandigarh project developer to pay over ₹56 lakh in interest to a homebuyer after rejecting the builder’s argument that the Covid-19 pandemic justified a multi-year possession delay. The ruling, dated July 19, 2026, found that the contractual possession deadline was June 2019 — nearly a year before pandemic-related restrictions came into effect in 2020. The Authority held that a force majeure event cannot be invoked to excuse a delay that had already commenced under normal conditions, setting a clear precedent for similar disputes. The homebuyer had entered into an agreement in 2015, paid a substantial portion of the ₹66 lakh consideration, and waited over seven years for possession. RERA also dismissed the developer’s arbitration clause defence, reaffirming its jurisdiction under Section 18(1) of the RERA Act regardless of contractual stipulations.

What this means for the trade: RERA authorities are taking a harder line on delay excuses — developer accounts with long possession backlogs are now more exposed to cash outflows through interest penalties, which can slow payment cycles to tile, sanitaryware, and finishing material suppliers on active projects.

Have a view on this report?

CeramicPost publishes selected responses from professionals working in the tile and building materials trade.

CeramicPost welcomes responses from trade professionals. Selected responses are published below the article with your name, designation, and company. Please use your company email address — submissions from personal accounts (Gmail, Yahoo, Outlook and similar) are not accepted.

0 / 1500
You will receive a verification email. Your response is reviewed before publication. See our privacy policy.
More news
Previous news
Companies & Brands
UltraTech Cement Posts Record Q1 FY27 - 17% Profit Growth, Wires & Cables Launch Confirmed
Jul 20, 2026
Next news
Industry & Market
Pune Office Leasing Surges 54% in Q2 2026 - GCCs Drive Record Commercial Demand
Jul 17, 2026
Free resources